License
Renewal Timeline |
| July 2005 |
Oyster Creek submits application for a 20-year
license renewal to the Nuclear Regulatory Commission (NRC).
|
|
| August 2005 |
NRC holds public meeting on license renewal
process. |
|
| October 2005 |
NRC hosts public meeting on audit results
of application methodology. |
|
| November 2005 |
NRC convenes public meeting on environmental
portion of application. |
|
| Winter 2005 - Spring 2006 |
NRC conducts inspection of Oyster Creek's
environmental and safety programs and practices. |
|
| April 2006 |
NRC discusses audit results of Oyster Creek's
aging management plan NRC public meeting. |
|
| June 2006 |
Draft environmental impact statement to be
released by NRC. |
|
| Summer 2006 |
Public comment period opens on draft environmental
impact statement. |
|
| Fall 2006 |
NRC continues inspection activities. |
|
| Winter 2006 |
NRC releases final environmental impact statement.
|
|
| 2007 |
NRC announces decision on application. |
|